Articles

Promote tested staging artifacts to production without rebuilding

Promote exact staging build artifacts and pinned non-secret config to production with `gregale environment promote --sync-config` while keeping production secrets separate, with dark health rounds, service-graph rewiring and migrations rolling out per account.

Updated

Promote the exact container artifact and pinned non-secret configuration you tested in staging straight into production with gregale environment promote—without rebuilding from source, leaking staging credentials, or shifting live traffic before dark candidates pass health verification.

Maturity: Artifact + config snapshot promotion works today on complete project HTTP graphs. Health-verified promotion (--verify), complete service-graph regeneration, migration promotion (--migrate), and push-worker promotion (--workers) are rolling out per account (ask support to enable them); staging-to-production production secret staging (--release-secrets-file) and combined --migrate --workers promotions are not available yet.

Why branch-per-environment rebuilds drift

On many PaaS platforms, moving from staging to production merges a Git branch and runs a second build. Even from the same commit, unlocked dependencies, base-image updates, build-time environment variables, or edited dashboard flags can mean production ships bytes that were never tested in staging.

Promote exact artifacts with pinned configuration

sh
gregale environment promote my-project --from staging --to production --sync-config --yes --wait

Gregale captures the complete active source HTTP release graph and its non-secret configuration snapshot, previews every changed key, and reuses the tested build artifact in production without rebuilding:

  • Secrets stay environment-owned: Production keeps its own secrets, secret version pins, authentication credentials, and infrastructure bindings—never overwritten by staging credentials.
  • Approval and preview-hash fencing: Protected production targets still enforce source qualification and approvals, and any variable or source change after preview invalidates the promote plan so stale approvals cannot apply.
  • Atomic rollback: If promotion fails verification or is cancelled (gregale environment cancel), Gregale restores the previous graph and pinned configuration together without overwriting newer intentional production edits.

Dark health verification, service graphs, migrations, and workers (per-account rollout)

Where enabled for your account, --verify adds pre- and post-cutover gates on read-only GET/HEAD probes (up to five project probes, minimum 21 minutes of revision retention):

bash
gregale environment preview shop --from staging --to production --sync-config --verify
gregale environment promote shop --from staging --to production --sync-config --verify --yes --wait --progress --timeout 25m
  1. Dark preflight: Candidates boot off live traffic and must pass two complete healthy probe rounds one minute apart (10-minute preflight deadline). Complete-graph mode rewires destination service URLs so private candidate services talk to candidate peers during preflight.
  2. Database expansion (--migrate, optional): Runs one backward-compatible release_command (up to 10 minutes) before candidate checks. Interrupted tasks never auto-replay blindly; inspect the database and run gregale environment migration recover --action resume|resolve with an explicit evidence hash.
  3. Workers (--workers, optional): Promotes up to 8 production push-queue workers alongside HTTP services, validating startup and real baseline queue deliveries before cutover (low traffic reports unknown and never fakes healthy).
  4. Atomic cutover + post-cutover verification: Traffic flips atomically, followed by two additional healthy rounds before finalizing.

Up to 8 active promotions and 32 queued requests (15-minute queue wait; 429 project_promotion_queue_full past capacity) are tracked durably on the server even if the CLI times out locally.

Boundaries to know before adopting

  • Pull/job workers, companions/sidecars, combined --migrate --workers in one promotion, promoting multiple workers concurrently from scratch, and staging destination secret rotations (--release-secrets-file) are outside verified promotion today.
  • Because rollback restores code and config rather than undoing committed SQL schema edits, keep --migrate release commands backward-compatible with both the old and candidate codebases.

See Environment promotion, Atomic project releases, Release safely, Canary deploys with automatic rollback, and Roll back a bad migration: code and database together.

Questions

Does promoting from staging to production rebuild the container image?

No. gregale environment promote --from staging --to production --sync-config reuses the tested staging build artifact and binds pinned non-secret variables without running a fresh build.

Do staging secrets overwrite production secrets during promotion?

Never. Production retains its own secrets, secret version pins, authentication credentials and service bindings while receiving only the promoted artifact and approved non-secret configuration.

Which verified promotion features require account enablement today?

Health-verified (--verify) two-round dark cutovers, complete HTTP service-graph promotion, database migration expansion (--migrate) and push-worker promotion (--workers) are rolling out per account (contact support); --release-secrets-file and combined --migrate --workers are not available yet.